Evaluate the completion of cellular storage in a warehouse

It is necessary to evaluate the improvements in the work of the cells
1. Loading cells.
Now it is possible to create cells manually using this functionality

It is necessary to evaluate the functionality of importing cells into the system, since now we plan to import about 3.5k cells, and doing it manually takes quite a long time. How much will it cost to finalize the functionality of importing cells through excel
I see it as the "Import" button -> the same as in the system directories.
2. Set up selling from a cell
- now if you post goods to a cell, and in the order display the "cell" field in the table, then you can see which cells the goods are in only by clicking on this field 2 times and select it yourself. But since we want to use cells for quick order picking, some kind of automatic cell selection functionality is needed.
That is, if the order contains a product that is located on a specific cell (or several), then automatically select any
Original question is available on version: ru

Answers:

One more improvement needed
Now there is an action "Create a product from materials" we use it in order to produce the missing goods in the order

But when returning, we encountered a problem that you need to unpack the goods back. Can we put into action "Production"
Add checkbox "Only those produced in this process"
That is, for these 2 actions to work together.
1st produces a commodity but only that which is not enough for sale
The 2nd, upon return, must decompose it back into components, but again, only those that were produced in this order
How many hours is this?
09.06.2021, 13:57
Original comment available on version: ru

Good afternoon.

Nikita Bidenko wrote:
1. Loading cells.

Finishing will take about 5 hours

Nikita Bidenko wrote:
2. Set up selling from a cell

If you do not select any of the cells, the box will still be able to sell the goods. Those. you do not have to select something in the field

Nikita Bidenko wrote:
Return of goods to the warehouse.
Now, when returning goods to the warehouse, the item is returned simply to the warehouse, without specifying a cell. It is necessary that in the action "Return the contents of the process to the warehouse" a checkmark "Return to the cell from which it was sold" appeared - > what hours is it?

can you create a test process and recreate the situation with one test product? How do you return an item? In theory, this shouldn't happen. Thank you.

Nikita Bidenko wrote:
One more improvement needed
Now there is an action "Create a product from materials" we use it in order to produce the missing goods in the order
But when returning, we encountered a problem that you need to unpack the goods back. Can we put into action "Production"
Add a tick "Only those that were produced in this process"
That is, for these 2 actions to work together.
1st produces a commodity but only that which is not enough for sale
The 2nd, upon return, must decompose it back into components, but again, only those that were produced in this order
How many hours is this?

in the production action, check the box "produce only the selected number of products" and in the order in the number of selected products write the required quantity for production.
10.06.2021, 17:31
Original comment available on version: ru


Now there is an action "Create a product from materials" we use it in order to produce the missing goods in the order
But when returning, we encountered a problem that you need to unpack the goods back. Can we put into action "Production"
Add a tick "Only those that were produced in this process"
That is, for these 2 actions to work together.
1st produces a commodity but only that which is not enough for sale
The 2nd, upon return, must decompose it back into components, but again, only those that were produced in this order
How many hours is this?

You answered:
in the production action, check the box "produce only the selected number of products" and in the order in the number of selected products write the required quantity for production.
The fact is that the production is now working correctly, we use the action, "Create a product from materials" and check the box "Produce only the amount of products that has not yet been produced in the current process". Thus, the system itself automatically pre-produces those positions that are not enough to sell this order. - there are no questions, everything works as it should.
We lack a return action, it turns out that if the product is canceled, then we need to unpack the positions back. Just returning it to the warehouse is not enough. Is it possible in the same action to add a checkbox "Unpack the goods that were produced by this action"?

So that we roll back the production operation exactly for those goods that were produced as part of this order
20.07.2021, 09:11
Original comment available on version: ru

To do this, there is the action "Production" with a checkmark "Reverse production (unpacking)"
20.07.2021, 10:53
Original comment available on version: ru

Doesn't work the way you described. Here is an example order
https://ppikc.crm-onebox.com/admin/customorder/bistraya-prodazha/373462/edit/
It clearly shows that at first the production of the goods took place (1 pc), it was originally in order 1
The production itself took place through the use of the procedure
https://ppikc.crm-onebox.com/admin/shop/workflow/19/procedure/34/?status=0
Next, we added a second item and used procedure 2
https://ppikc.crm-onebox.com/admin/shop/workflow/19/procedure/35/?status=0
There is a setting in it so that the reverse unpacking occurs. It happened, but it happened for ALL products in the order, and in fact only 1 was originally produced. We need a setting that will reverse-decompress ONLY the products that were produced as part of this process.
Can you evaluate and refine such a setting?
07.08.2021, 16:49
Original comment available on version: ru

Yes, it will take 2 hours
09.08.2021, 12:54
Original comment available on version: ru


Good afternoon
do you have a fix for the answer? Will it happen or not, and if so, when?
16.08.2021, 09:45
Original comment available on version: ru

Good afternoon. I finalized the checkbox in the action settings, please try it - is it what you need. Thank you.
20.08.2021, 13:17
Original comment available on version: ru

I tried on the order example
https://ppikc.crm-onebox.com/admin/customorder/order/370324/edit/
Procedure
https://ppikc.crm-onebox.com/admin/shop/workflow/14/procedure/33/?status=0
It turns out that the checkbox itself is called how to launch an action on goods for which there were no warehouse operations, but it is necessary just differently. Maybe I didn’t set it up that way, but now it doesn’t work in a specific order
If there are 10 items in the order, and I only produced 1 item, then I only need to unpack it back.
That is, as I wrote above - so that during the production of goods in the process I could unpack only those goods that were produced.
Simple logic - in order to sell a product to a client, I assembled a set of products (production), then the client refused and I need to return the individual components of this set to the warehouse. But in addition to them, there are 5 more goods in the order - which are not produced at all and were not produced at all, I want to cancel the reserve of goods and return the set to the warehouse, but the reverse production action checks all the passports and does not allow production.

I don't know how to describe it to you in more detail.
20.08.2021, 20:18
Original comment available on version: ru

Good afternoon. I'm sorry, I misread the condition and mixed up which were produced and which were NOT produced. Updated your project after the fix.
23.08.2021, 12:55
Original comment available on version: ru

Hello, the checkmark is called correctly, but the action does not work (
Same order
https://ppikc.crm-onebox.com/admin/customorder/order/370324/edit/
In warehouses we see 2 production operations

We use the procedure with such settings
https://ppikc.crm-onebox.com/admin/shop/workflow/14/procedure/33/?status=0

But when clicking, we get an error
24.08.2021, 09:15
Original comment available on version: ru


https://ppikc.crm-onebox.com/admin/customorder/order/370324/storage/ on this page you can see that the production takes place not in process #370324 but in another, most likely in the child. The process product of the child process has nothing to do with the products of the process in the current one. Those. it is in the current process that you have produced nothing.
27.08.2021, 16:30
Original comment available on version: ru

You are inattentive
The process is the same, we just write the order number from the site in the name of the process, because of this you most likely thought that the production took place in the wrong place, please look again
27.08.2021, 17:50
Original comment available on version: ru



I take care of your task
09.09.2021, 10:41
Original comment available on version: ru

Fixed this problem, now you need to specify passports in 2 products, according to which you will unstack them
09.09.2021, 11:05
Original comment available on version: ru


anonymous duck
OneBox production
Employee wrote:
Fixed this problem, now you need to specify passports in 2 products, according to which you will unstack them

https://ppikc.crm-onebox.com/admin/customorder/order/370324/edit/
in the order (example) of the product passport are entered
but it does not allow to unstack the goods - why? Or is there some other field that needs to be filled in? Now indicated in the "Product Passport"
09.09.2021, 11:55
Original comment available on version: ru

This has been corrected. Now he writes that there are not enough goods in stock, since 24 pieces of goods https://ppikc.crm-onebox.com/admin/shop/products/2289/storage/ are already reserved in another order
09.09.2021, 12:59
Original comment available on version: ru

now the logic itself is working correctly - there is 1 moment left - if there are no production operations for products at all in the order - then it does not allow you to go to the stage and writes that the product does not have a passport - but as if there are goods in the system without a passport at all and this is normal . You need some kind of setting so that it skips to the stage even if there is an error or to ignore goods that do not have a passport - then it will work perfectly
27.09.2021, 11:05
Original comment available on version: ru

Yes, in 1 hour you can make such a setting so as not to show an error if some product does not have a passport and, accordingly, it does not need to be produced / dismantled. Bill?
27.09.2021, 17:19
Original comment available on version: ru



anonymous duck
OneBox production
Employee wrote:
Yes, in 1 hour you can make such a setting so as not to show an error if some product does not have a passport and, accordingly, it does not need to be produced / dismantled. Bill?

Can you invoice?
08.10.2021, 10:15
Original comment available on version: ru

Doesn't work, throws an error
https://ppikc.crm-onebox.com/395410/
Press procedure "to cancel"
Here one more will be executed
https://ppikc.crm-onebox.com/app/workflow/14/procedure/33/
There set 2 of these settings in production action

That is, there are no warehouse operations and no production passports - but for some reason the system gives an error, correct it?
There is a checkbox "run the action only for process products that participated in other warehouse operations of the process" and there are no warehouse operations in the order, but the error is still there
24.11.2021, 12:44
Original comment available on version: ru


Nikita Bidenko wrote:
Doesn't work, throws an error
https://ppikc.crm-onebox.com/395410/
Press procedure "to cancel"

I don’t quite understand, at this stage, the check for the field is configured. It throws an error because The field is not filled.
https://ppikc.crm-onebox.com/admin/shop/workflowstatus/91/action/new/
24.11.2021, 17:22
Original comment available on version: ru

Try this order
https://ppikc.crm-onebox.com/395984/
Here is such an error
26.11.2021, 09:14
Original comment available on version: ru

I clicked "To cancel" in this process, it went to the stage without errors
26.11.2021, 11:46
Original comment available on version: ru


Zamogilny Dmitry
OneBox production wrote:
I clicked "To cancel" in this process, it went to the stage without errors

Here is 1 more order
https://ppikc.crm-onebox.com/392552/
The same error, I don’t know how it works, but there is an error, a couple of hours pass and it passes, there are a lot of orders to cancel
check this one
27.11.2021, 11:33
Original comment available on version: ru


anonymous duck
OneBox production wrote:
Yes, in 1 hour you can make such a setting so as not to show an error if some product does not have a passport and, accordingly, it does not need to be produced / dismantled. Bill?

Actually, the revision concerned ignoring this particular error.
Lack of products for production is another.
Do you need other errors to be ignored as well?
27.11.2021, 21:17
Original comment available on version: ru

and the first tick then what for is necessary?

if the goods did not participate in other warehouse operations - before the action is performed, the action is to remove the reserve from the goods, and there are no sales of goods within the order. That is, according to the order, there are no warehouse operations - why does it then perform this action at all?
And now it turns out that we have completed 2 checkboxes that do not work, but I don’t know what other errors there may be, they appear later, now we’ll fix this error, there will be some more ...
You can fix it so that it simply conducts the reverse production warehouse operation only THEN, when there was the first production operation and that's it, these checkboxes are needed ONLY in order to unpick back those items that were produced, I don’t know how else to explain what needs to be done.
29.11.2021, 09:40
Original comment available on version: ru

We have corrected that if the checkbox "run the action only for process products that participated in other warehouse operations of the process" is enabled and the corresponding process products are not found, the action will not generate an error, it will not work.
14.12.2021, 11:33
Original comment available on version: ru

Please join the conversation. If you have something to say - please write a comment. You will need a mobile phone and an SMS code for identification to enter. Log in and comment