Good afternoon. Please tell me how to set up an action to automatically transfer the BP if the status of the BP does not change for some time, for example 4 days.
We have an automatic return of parcels by new mail on day 5, we want to do this if the order is not picked up on day 4, hangs at the "Sent" stage and is not transferred further, then the system switches from "Sent" to "Risk of return" on day 4 automatically.
Searched in action but to no avail.
Good afternoon. Please tell me how to set up an action to automatically transfer the BP if the status of the BP does not change for some time, for example 4 days. We have an automatic return of parcels by new mail on day 5, we want to do this if the order is not picked up on day 4, hangs at the "Sent" stage and is not transferred further, then the system switches from "Sent" to "Risk of return" on day 4 automatically. Searched in action but to no avail.
Thank you, in principle it almost fits, but the situation turned out to be a little more complicated. The condition must be met: 1. Stage BP "Sent" 2. The stage of the TTN of the parcel must be in the status "Arrived at the office" 3. From the moment the parcel arrives, a period of 3 days is set 4. If the stage has not changed to received, on the 4th day (from the moment the TTN stage was changed), the system switches from the "Sent" stage to the "Not picked up" stage In simple words, we want that on the 4th day after the parcel arrived at the department, the stage would change. How to implement such a mechanism?
Thank you, in principle it almost fits, but the situation turned out to be a little more complicated.
The condition must be met:
1. Stage BP "Sent"
2. The stage of the TTN of the parcel must be in the status "Arrived at the office"
3. From the moment the parcel arrives, a period of 3 days is set
4. If the stage has not changed to received, on the 4th day (from the moment the TTN stage was changed), the system switches from the "Sent" stage to the "Not picked up" stage
In simple words, we want that on the 4th day after the parcel arrived at the department, the stage would change.
How to implement such a mechanism?
Thank you, and from what moment does the countdown of the action "set the deadline for the stage" begin? Since the time when the process is transferred to a new stage or at a certain time like 00:00 ?
Thank you, and from what moment does the countdown of the action "set the deadline for the stage" begin?
Since the time when the process is transferred to a new stage or at a certain time like 00:00 ?
As far as I can see you have already answered this question in the chat. Why does it make sense to ask the same question in 2 places at the same time without waiting for an answer in the first source?
As far as I can see you have already answered this question in the chat. Why does it make sense to ask the same question in 2 places at the same time without waiting for an answer in the first source?