hello. Bulk change of process products by loading xls file overwrites the value in the products table, but does not overwrite the value in the final part of the process. This introduces confusion, because in the free table of processes in the sum field, a figure is displayed from the final part of the process and it is not clear whether the process products were overwritten or not
[file]4578[/file]
[file]4579[/file]
hello. Bulk change of process products by loading xls file overwrites the value in the products table, but does not overwrite the value in the final part of the process. This introduces confusion, because in the free table of processes in the sum field, a figure is displayed from the final part of the process and it is not clear whether the process products were overwritten or not
Tyndyk Maxim Vadimovich wrote: If yes, please indicate what you are doing.
through the block to update the process products of the bulk operations panel, I load the xls file from two lines - the id of the process product and the new value of its price. At the same time, the price and, accordingly, the cost in the process block, the product table is updated, but not in the final part of the process (as shown in the first screen)
[quote]
Tyndyk Maxim Vadimovich wrote:
If yes, please indicate what you are doing.
[/quote]
through the block to update the process products of the bulk operations panel, I load the xls file from two lines - the id of the process product and the new value of its price. At the same time, the price and, accordingly, the cost in the process block, the product table is updated, but not in the final part of the process (as shown in the first screen)
Hello, the issue has been resolved. For the test, I checked in the process 96598 (I attach the file below), when the price of the product of the process changed, a recalculation was performed and the final cost was correct
Hello, the issue has been resolved. For the test, I checked in the process 96598 (I attach the file below), when the price of the product of the process changed, a recalculation was performed and the final cost was correct
[file]4730[/file]