Hello, how to set up the system so that you can go to a certain stage only on the day the process is created?
The situation is such that on the day the process is created, it may be necessary to transfer the process to failure, on other days this can no longer be done.
Therefore, we need the opportunity only on the day of process creation to be able to transfer users to the ERROR stage
Thanks in advance for the extended answer..
Original question is available on version: ru

Answers:

you can create an additional field with the date type - , at the initial stage write the current date into this field, for example, by this action - https://prnt.sc/vppey8 , and at the Error stage set the action - https: //prnt.sc/vppfnx
if the field is of the date and time type, it will not work correctly, since, for example, the creation date will be 2020-11-25 10.00 , and you switch the stage after 10 minutes, the action will generate an error
25.11.2020, 11:52
Original comment available on version: ru

Marina, we need the button to not even appear if the date is no longer the current date of adding the process, we are trying to simplify the work of users in the system, and so that there are no extra buttons that it’s pointless to press ...
25.11.2020, 12:54
Original comment available on version: ru

set the duration of the stage, for example, 12 hours, and after this period, switch to some intermediate stage, where there will be no connection with the stage Error and the button for switching to this stage will not be displayed on it
25.11.2020, 13:37
Original comment available on version: ru


Mulach Marina Anatolievna
Employee wrote:
set the duration of the stage, for example, 12 hours, and after this period, switch to some intermediate stage, where there will be no connection with the stage Error and the button for switching to this stage will not be displayed on it

Marina, it’s not very convenient, you don’t need to change the BP stage, but remove the connection with the stage over time ...
25.11.2020, 15:13
Original comment available on version: ru

at the moment, it is not possible to remove the connection with the stage after a certain period of time
25.11.2020, 15:23
Original comment available on version: ru


Mulach Marina Anatolievna
Employee wrote:
at the moment, it is not possible to remove the connection with the stage after a certain period of time

It's just that at any stage we need to have such an opportunity to go to the stage if the date is current. Please estimate the cost of refining this feature... In the previous system, we could set it up... SO that, depending on the date, it was possible to change links with the process. Now it's very inflexible that only a direct link is obtained and there is no way to remove the link depending on the conditions ...