A bug in an already configured process during implementation (work with product assembly)

A bug in an already configured process during implementation
The sum of the cost of the components is not copied in the assembly cost field (of the future product passport). Below is a step-by-step description:
1) I create an assembly (bouquet)
https://drevojelaniy.crm-onebox.com/admin/shop/customorder/add/?type=sozdanie-bu...
screenshot https://prnt.sc/ug1e9c
2) I click "fold the products into the finished product"
screenshot https://prnt.sc/ug1gv9
In the universal block on the right, in the "Cost of the bouquet" field, the price of the components is summed up.
This amount should be automatically copied into the "cost" field!
(*I fill in the "sale price" field manually - in this field the amount should also be copied by default from the "price of the bouquet".)
3) I click the "done" button. For further sale of the finished assembly (bouquet) in the process of sale.
4) Forming a sale https://drevojelaniy.crm
Original question is available on version: ru

Answers:

It is necessary to fix it so that the price is pulled up from the "SALE PRICE" screen https://prnt.sc/ug1gv9 ***
12.09.2020, 16:14
Original comment available on version: ru

From what I can see, you are creating a new product based on components.
The purchase price of the product is formed from the purchase price of the components, but in order to prescribe the sale price, you need to add a few actions)
1. Create additional. process product field (price_DOP)
2. Through the action "Write a value in the additional field of the process product based on the formula"
write to this created add. field -> value with add. process fields (shown on the screen)
3. Using the "copy process product fields" action, write the price_DOP value in the "price" and "process product price" fields
Thus, the value that you have displayed will be recorded in the price of the product, which will allow the system to automatically calculate the "Cost" + this value will also be displayed in the product card itself
PS Since there can be a lot of configuration options, and the person who was involved in the implementation may have provided for this functionality, but implemented it somehow differently -> I voiced the first option that came to mind)
14.09.2020, 09:03
Original comment available on version: ru

Dear Sergey Yurievich,
Please ask questions in separate threads.
The point is that you asked three questions in one thread:
1. It is necessary to fix it so that the price is pulled up from the "bouquet cost" screen https://prnt.sc/ug1gv9
2. Automation "print price tag" does not work https://prnt.sc/ug1zh6
3. PS - what to do with product passports (bouquets) after the sale of the assembly?
Answers on the forum are paid to employees and partners from OneBox,
and the reality is that no one here will answer three questions at once, because no one wants to do their job 3 times cheaper.
14.09.2020, 09:03
Как со мной связаться - никак :)
Задавайте вопросы на форуме публично - и я отвечу.
Подробнее - https://1b.app/ru/user/11/
Original comment available on version: ru


Gubko Alexander Sergeevich Employee wrote:
From what I can see, you are creating a new product based on components. The purchase price of the product is formed from the purchase price of the components, but in order to prescribe the sale price, you need to add a few steps)1. Create additional process product field (price_DOP)2. Through the action "Write value in the additional field of the process product based on the formula", write in this created add. field -> value with add. process fields (shown on the screen) 3. Using the "copy process product fields" action, write the price_DOP value in the "price" and "process product price" fields. Thus, the value that you have displayed will be recorded in the price of the product, which will allow the system to automatically calculate " Cost" + in the product card itself, this value will also be displayed PS Since there can be a lot of configuration options and the person who was involved in the implementation may have provided for this functionality, but implemented it somehow differently -> I voiced the first option that came to head)

It seems to have done. Please check, is it correct?
At the stage "fold the products into the finished product."
"2. Through the action "Write a value in the additional field of the process product based on the formula"
write to this created add. field -> value with add. process fields (shown on the screen)"
Seems like he did it right. Screen https://prnt.sc/uh3h2y
"3. Using the "copy process product fields" action, write the price_DOP value in the "price" and "process product price" fields
Did. Screen https://prnt.sc/uh3hta
"1. Create an additional field for the product of the process ( price_ADV )"
I don't understand :-( Please elaborate.
14.09.2020, 17:50
Original comment available on version: ru

try to create now you specified the actions correctly, but inserted the wrong variables
15.09.2020, 11:52
Original comment available on version: ru